城外国际绿洲之园公寓项目进度播报
Wild Urban International Oasis park project progress report
从规划的蓝图愿景到如今的建筑实景,每一份期待都是前行的动力,每一份努力只为不负所盼,我们承诺在一砖一瓦中变为现实。
From the blueprint vision to the actual construction today, every expectation of yours is the driving force to move forward. Every effort we make is to live up to your expectations, and we promise to make it a reality brick by brick.
截止到2021年10月30日,整体外墙结构已搭建完成。
As of October 30, 2021, the overall outer wall structure has been built.
截止到2021年12月30日,项目所需的使用到的进口材料已进场。
As of December 30, 2021, the imported materials required for the project have been to the site.
截止到2022年1月5日,现场室内水电安装以及天花吊顶已基本完成,外墙涂料正在行进中。
As of January 5, 2022, the interior plumbing and electrical installation as well as the ceiling ceiling have been basically completed on site, and the exterior wall coating is in progress.